Legislative Title:
|
Resolution approving Contract Change Order No. 1, approving the Notice of Acceptance and Completion of the contract between the County of Nevada and Perimeter Security Group, LLC. for Phase II construction of a new perimeter fence and gate system at the Nevada County Airport (Res. 17-421), directing the Clerk of the Board to record this Notice in accordance with Civil Code Section 9208, authorizing the Chair of the Board of Supervisors to execute the Change Order reducing the contract price to $974,289.63, and authorizing the Airport Manager to execute Federal and State grant reimbursement documents related to the Phase II perimeter fence project. (Airport)
|